Summary
The city wrapped up this year's chip sealing of residential streets, swapping some streets out of the program (Ida Street in; Lincoln and Manitowoc streets out) at no extra cost. The final $55,716 payment closed out the contract.
At a glance
- Total mentions
- 5
- Last 30 days
- 2
Rising — discussed at 4 meetings since Sep 8, 2026, up from 0 in the two months before.
Impact analysis
Final contract payment of $55,716 with no change in total cost.
Residents of the streets that were chip sealed this year.
Mentions & discussions (5)
Board of Public Works - Nov 2, 2026
The public works report shows Valley Road reconstruction finishing by mid-November, Eighth and Third Street work done, and Racine Street pavement markings delayed to spring 2027.
Board of Public Works - Oct 19, 2026
A $72,052.50 progress payment to Donald Hietpas & Sons keeps the 2026 utility construction work moving.
Board of Public Works - Sep 21, 2026
The city is paying out progress payments on its 2026 utility construction work. This payment keeps the project moving — it's part of ongoing utility infrastructure work already under contract.
Board of Public Works - Sep 8, 2026
The city wrapped up this year's chip sealing of residential streets, swapping some streets out of the program (Ida Street in; Lincoln and Manitowoc streets out) at no extra cost. The final $55,716 payment closed out the contract.
Board of Public Works - Jul 6, 2026
The city paid its contractor $222,504.60 for utility construction work under the 2026 program, keeping underground infrastructure improvements moving.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Menasha
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.